Assignment description:
Dagny/Eirin main milestones:
DG2: December 2011,
DG3: December 2012,          
DG4: December 2016
Contract award Jacket: June 2012
Jacket installation: summer 2014
Start pre-drilling: summer 2014
Platform deck installation summer 2016

Project description:
Dagny is an oil and gas field located 30 km north of Sleipner and Eirin gas/condensate field is located 35 km north of Sleipner and 9 km from Dagny. Water depths approximately 116m
The Dagny development comprises a platform for oil stabilisation. The oil is exported to a floating storage unit (FSU), approximately 2.5 km away, where the oil is off-loaded to a shuttle tanker at suitable intervals. The rich gas is exported to Sleipner, where it is processed. The dry gas is exported to the Gassled system, and the condensate is exported in the Sleipner condensate pipeline to Kårstø. The Sleipner condensate train on Kårstø is used to split the condensate into different sales products.
The Eirin development project is a 4 slot subsea template tied in to Dagny platform by a 9 km flow line. There will be drilled 2 production gas wells. The Eirin gas production will mainly be used as injection gas on Dagny.
The position includes the following tasks/responsibilities;
Manage the Cost Control function in the project
Assist project management in establishing a decision basis for DG3 and PDO documentation.
Establish and update the project control basis for the project.
Maintain the WBS and task structure in PIMS and SAP for the Feed phase
Establish WBS structure and task structure in PIMS and SAP for execution phase.
Contribute in contract formulation and evaluation.
Responsible for collection of monthly cost and progress information and prepare a total monthly project status (cost, progress and prognosis) including variance analysis and trend analysis.
Compile and issue monthly reports.
MIS status reporting
Estimating of accruals
Coordination of the half-yearly current control estimate updates (CCE)
Establish work program and yearly budget for the project
Maintain prognosis and variance analysis against the approved budget
Contribute to change management in the project
Estimating of cost consequence of project changes
Maintain the Master Control Estimate
Close-out of contracts and finalizing of all relevant project close-out activities.
Participate in other Cost Control issues and together with the Project Control Team constribute to coordinated and good work-processes in the interface towards defined stake holders.

Competence requirements:
University- or college education.
Relevant extensive experience may compensate for lack of formal education.
Cost Control experience from FR05 projects. Skilled SAP and PIMS knowledge.
Independent and resourceful.
- Excellent social skills
- Creative and analytical
- Flexible
- Excellent communication and writing skills in both Norwegian end English.

Language requirements (if essential for the work):
Norwegian, English

Workplace:        
Onshore, Stavanger

Commuters accepted: Yes

Work percent:   100%
 

Svarfrist: ASAP og senest innen 20.02.12

Contiki Ressurser er en aktiv aktør i et spennende og dynamisk marked. Hos oss vil du bli del av et bransjemiljø og ha gode muligheter for faglig utvikling. Vi tilbyr konkurransedyktige betingelser, samt gode pensjons og forsikringsordninger. Ta kontakt på telefon 55 70 63 31 / 982 36 403 hvis du vil ha mer informasjon, eller send CV til konsulent@contikiressurser.no

Webdesign, utvikling og publiseringsløsning av Keyteq AS